Breathe · Interactive prototype

From accepted quote to a lime‑plastering schedule of works

Solid walls need lime — and lime sets its own pace. This tool reads the quote from Notion, checks photos of every wall, and builds a visit-by-visit plan around carbonation time, so the schedule is honest about both labour days and calendar days.

01Import quote 02Photograph areas 03Confirm features 04Review schedule 05Issue works order
16 jump between screens

Clickable prototype · V1 concept · July 2026 · Prepared for Chris & Mario · Confidential

BreatheLime works D

Jobs

Lime plastering · V1
Active jobs
6
3 scheduled · 3 on site
Awaiting photos
2
Blocking schedule drafts
Drafts to review
1
The Old Rectory · 3 flags
Schedule accuracy
87%
52 eval examples · +6 this week
JobQuoteStageConfidenceNext action
BreatheLime works Jobs / New schedule M

Which quote are we scheduling?

Accepted quotes sync from Notion automatically. Pick one and check the scope looks right before we move to photos.

Step 1 of 4
BreatheLime works The Old Rectory / New schedule M

Add a photo of every wall and ceiling

The system looks for what slows lime work down — cement render to hack off, salt and damp staining, sockets, windows and chimney breasts. Anything you skip gets flagged on the schedule as an estimate.

Living room

4 of 4 areas photographed
Chimney wall
Chimney wall● Ready
Window wall
Window wall● Ready
Party wall
Party wall● Ready
Ceiling — lath & plaster
Ceiling● Ready

Hall

0 of 2 areas photographed

Stair wallClick to add a photo

Stair wall● Missing

Front wallClick to add a photo

Front wall● Missing
4 of 6 areas · missing photos are flagged on the schedule
BreatheLime works The Old Rectory / New schedule M

Does this look right?

We've scanned each photo for what changes a lime schedule. Check the counts — fix anything that's wrong. It takes seconds and it's how the system learns the house.

Area 1 of 3
Living room · chimney wall
Cement render · 94%
Cement render · 91%
Chimney breast · 62%
Damp / salt staining · 71%
Socket · 96%
Step 3 of 4 · area 1 of 3
BreatheLime works The Old Rectory / Draft schedule v1 MC

Schedule of works — living room & hall

Hack off cement · three-coat haired lime (NHL 3.5) · limewash — generated 4 Jul from the Notion quote and 13 confirmed features
3 items need review
Quote
£9,480
On-site labour
8days
Elapsed time
24days · 3 visits
Rough calc said
12days, one block
Coverage
6/6areas photographed

1Preparation & protection0.5 days

1.1Sheet floors and stair, protect joinery and fireplace2 roomsFireplace 88%2 hConfident
1.2Isolate and cover 3 sockets, drop radiator3 sockets1 radiator1 hConfident
1.3Confirm radiator removal with customerNot in quoteCheck quote

2Removal & substrate2 days

2.1Hack off failed cement render, both walls≈ 19 m² detected1.5 daysConfident
2.2Rake out joints, brush down, clear wasteQuote line 20.5 dayConfident
2.3Treat hygroscopic salts at chimney baseDamp staining 71%+0.5 dayLow confidence

3Repairs & dubbing out1 day

3.1Re-fix sagging laths, replace splits (ceiling)Sagging 66% · ≈ 4 m²0.5 dayLow confidence
3.2Dub out deep voids with haired coarse stuffQuote line 30.5 dayConfident

4Scratch coat1.5 days

4.1Haired NHL 3.5 scratch coat, walls & ceiling31 m²Lime labour constants1.5 daysConfident
Carbonation — 7 days minimum before the float coat. No work on these walls; keep ventilated.

5Float coat1.5 days

5.1Haired float coat, rule flat, key for finish31 m²1.5 daysConfident
Carbonation — 7 days minimum before the finishing coat.

6Finish & decoration1.5 days

6.1Fine lime skim finishing coat31 m²1 dayConfident
6.2Limewash ×3 coats, refit radiator & sockets, handoverQuote line 60.5 dayConfident
BreatheLime works The Old Rectory / Works order Approved by Chris · 4 Jul

Works order · Lime plastering

The Old Rectory — living room & hall

Mon 6 – Wed 29 Jul · 8 labour days · 3 visits Crew: 2 plasterers Quote £9,480 Customer: R. Whitfield · home Mon–Fri

Visit 1 — strip, repair, scratch coat

Mon 6 – Thu 9 Jul4 days on site
Day 1
Mon 6 Jul

Preparation & protection

Day 2
Tue 7 Jul

Removal & substrate

Day 3
Wed 8 Jul

Repairs & dubbing out

Day 4
Thu 9 Jul

Scratch coat

Carbonation — Fri 10 to Thu 16 Jul (7 days, no site work)

Scratch coat cures. Customer briefed: keep windows cracked open, no heating blast on the new coat, mist if it's drying pale and fast. Crew is booked at 14 Chapel Row this week.

Visit 2 — float coat

Fri 17 – Mon 20 Jul1.5 days on site
Days 5–6
Fri 17 · Mon 20

Float coat

Carbonation — Tue 21 to Sun 26 Jul (6–7 days, no site work)

Float coat cures before the fine finish goes on. Same customer brief as visit 1.

Visit 3 — finish & decoration

Mon 27 – Wed 29 Jul2.5 days on site
Day 7
Mon 27 Jul

Finishing coat

Day 8
Tue 28 – Wed 29

Limewash & handover